VCP - Jacareí
Client: |
Votorantim Celulose e Papel - VCP. |
Segment: |
Paper and Cellulose |
Timeframe: |
32 months |
Volume: |
8.773 m3³ vol. Concreto |
Location: |
Jacareí | SP |
Client:
Votorantim Celulose e Papel - VCP.
Segment:
Paper and Cellulose
Timeframe:
32 months
Volume:
8.773 m3³ vol. Concreto
Location:
Jacareí | SP
Scope
Manufacturing, supply and installation of roof and siding steel structure. Civil services for expansion of Project P-2000 - Package 4 - bases, slabs and walls for Recovery Boiler, Pulp Storage Building, power substations, tank bases, and several bases on the plant. Construction of new external accesses and adjoining yards, earthworks, bases, sub-bases and drainage for wood yard.